Preliminary plan:

 

 2013 December Workshop on STXM, Umeå
Fri 13th December Funding decision by VR
 2014 Spring Start project 1st of April
Summer/Autumn Conceptual Design Report
 2015 Summer Detailed design report: optics & ID
Autumn Finalize BL optics design – start procurement optics systems (excl. KB-pair)
  Optics hutch procurement
 2016 Spring Infrastructure: hutches design
Workshop on CXI, Lund
Order optics systems
Summer Install: optics hutch
Front end procurement
Design reviews optics systems -> production
Autumn Install: experiment & user hutches
Water-cooled optics procurement (M1, M2)
Winter Optics procurement, continued (M3)
Infrastructure: definition/installation
Define end-station STXM parameters
2017 Spring Final design review ID
Summer Delivery: Front end
Autumn/winter Finalize STXM end-station design
Delivery: Optics systems
 2018 Spring SAT + Install optics systems
STXM parts purchase
Summer Install Front end, install ID vacuum chamber
Delivery: STXM parts -> assembly
Install optics + alignment
Optics procurement: KB, design chamber
Autumn/winter Assemble beamline vacuum & stands
Design CXI station
Delivery & installation: undulator
 2019 Spring Early 2019: first light on STXM
Finalize CXI end station design: purchase parts
Summer (Friendly) User operation STXM
Autumn/winter Delivery: KB-mirrors, chamber -> SAT + align
Late 2019: assembly CXI end station – testing