2017
Q1Q2Q3Q4
BL components installation and alignment Cabling, PLC installation, control system development, work with end stationsMONO alignment, pumping and baking of all sections and end stations Undulator installation, motion tests of all components, more work on the control system
2018
Q1Q2Q3Q4
Further upgrade and commissioning (without X-rays) of the end stations: UHV-PES (former D1011), LDM-PES (former I411)Awaiting radiation safety permit, keep working with end stations, commissioning with laser lightAwaiting radiation safety permit, keep working with end stations, gas system installationCommissioning of the BL and end stations with X-rays, gas system installation
2019
Q1Q2Q3Q4
Commissioning continues with commissioning expertsFirst experiments in the UHV-PES and LDM-PES end stations, installing chopper on the gas-phase branchCommissioning users in the UHV-PES and LDM-PES stations, first experiments with ICE setupRegular user operation