Preliminary timeline for the DanMAX beamline project:

  • Optics procurement: 2017 Q4 – 2018 Q1
  • Detailed instrument design: 2018 Q1-Q2
  • Instrument procurement: 2018 Q2-Q4
  • Optics installation: 2018 Q4 – 2019 Q1
  • Insertion device installation: 2019 Q1
  • Commissioning: 2019 Q1-Q3
  • Transition to user program: 2020 Q1