Achieved and planned activities and milestones through the years.

2017
Q1Q2Q3Q4
First light in Optics hutch (OH)First XANES spectrum in OHWaiting for transfer pipeWaiting for transfer pipe - arrived in Dec
2018
Q1Q2Q3Q4
Installation of beam transfer pipe Awaiting radiation permitAwaiting radiation permit - granted in SeptemberCommissioning of end station with X-rays
2019
Q1Q2Q3Q4
Commissioning XASCommissioning expert users XAS
- Installation of XES spectrometer during summer shutdown
- Regular users XAS
- Regular users XAS
- Commissioning XES
- Commissioning XRD
2020
Q1Q2Q3Q4
- Installation Cryostat and HR mirror
- User operation XAS
- User operation XAS
- Expert users XRD
- Comm XES
- Commissioning Cryostat and XES
- Summer shutdown
User operation XAS