2016
Q1Q2Q3-Q4
Installation of opticsCommissioning of optics/controls without x-raysInstallation of in-vacuum wiggler
Commissioning of optics/controls without x-rays
2017
Q1Q2Q3Q4
Commissioning of optics/controls with x-raysCommissioning of monochromator/controls with x-raysSummer shutdown from 3 July-12 NovCommissioning of end station with x-rays
Installation of end station XASCommissioning users
2018
Q1Q2Q3Q4
Commissioning users & first usersUsers from 1st callInstallation of end station XES