2016
Q1Q2Q3-Q4
Installation of opticsCommissioning of optics/controls without X-raysInstallation of in-vacuum wiggler
Commissioning of optics/controls without X-rays
2017
Q1Q2Q3Q4
Commissioning of optics/controls with X-raysCommissioning of monochromator/controls with X-raysSummer shutdown from 3 July-12 Nov
Installation of end station XAS
2018
Q1Q2Q3Q4
Installation of pipe Awaiting permitAwaiting permitCommissioning of end station with X-rays, Commissioning users
2019
Q1Q2Q3Q4
Commissioning users XASCommissioning users XAS
Installation of XES spectrometer - summer shutdownUsers XAS,